Kansas Hydrovac & Excavation Regulations
Excavation laws, 811 requirements, and licensing information for Kansas.
Kansas requires excavators to contact Kansas 811 at least 2 business days before digging. The Kansas Underground Utility Damage Prevention Act establishes the state's dig safely framework.
Hydrovac excavation is essential in Kansas for oil and gas pipeline work and urban utility projects. The state's extensive underground pipeline infrastructure requires careful excavation practices.
Call Before You Dig: Kansas 811
Phone: 811 | Notice Required: 2 business days
Visit Kansas 811 WebsiteTolerance Zone
Careful hand excavation required within 24 inches of marked underground utilities.
Key Regulations
Kansas Underground Utility Damage Prevention Act
Primary excavation safety statute requiring notification and safe digging practices.
KSA 66-1801 et seq.
Marking Standards
Utilities must be marked using APWA uniform color codes within 2 business days.
Damage Notification
Excavators must immediately notify the facility owner and 911 if a gas line is damaged.
Penalties for Violations
Kansas imposes penalties for excavation violations.
Maximum Fine: $10,000
- ●Liability for facility repair costs
- ●Possible misdemeanor charges for negligent violations
Licensing Requirements
- Kansas contractor license for applicable work types
- Municipal permits and business licenses
- Adequate liability insurance coverage